Shuttabloc® at new TEG Biogas plant in Dagenham

Posted on: July 12th 2013    •    Posted in: Case studies, Retaining Walls, Shuttabloc
Precast Retaining Wall - Concrete dividing walls

Poundfield Precast have supplied and installed approximately 250 linear metres of Shuttabloc® walling for food and green waste at the new TEG Environmental Biogas plant in Dagenham. The wall heights varied from 3 metres to 5 metres.

Nial Rees of TEG says: ‘Poundfield’s new Shuttabloc system played a part in reducing the build time for the facility in comparison to traditional casting on site. The precast solution enabled works to carry on throughout the winter when an on site pour would have been severely disrupted. We have been impressed by the speed and quality of the Shuttabloc system, and will be looking to work with Poundfield in the future’.